Sample Quality Plan and Quality Audit for a Building
To Download the formats, Click (Download).
Sample Quality Plan (Download)
S.No. |
ITEM |
VERIFICATION/ INSPECTION
ACTIVITY |
REMARKS |
1 |
Steel |
Delivery challan, Material
Transfer Order, Test Certificate (Depending on the purchase order), Lab
reports. |
Only when asked for. |
2 |
Cement |
Delivery challan, Material
Transfer Order, Lab reports for fineness, hardness, grade sizes, final and
initial setting time. |
Only when asked for. |
3 |
Sand |
Sieve analysis, Silt content |
After initial sample is approved,
a random check will be done |
4 |
Jelly |
Sieve analysis |
After initial sample is approved,
a random check will be done |
5 |
Concrete Blocks |
Lab reports for compression
strength |
|
6 |
Lime |
Fineness |
|
7 |
Marble |
Visual inspection for grains,
whiteness and cracks |
As per the sample available |
8 |
Granite |
Check for quality, colour and
cracks |
As per the sample |
9 |
Tiles |
Size variation and visual
inspection for damages |
As per the sample |
10 |
Teakwood |
Check for seasoning, cracks and
fungus |
|
11 |
Flush Doors |
Check for size, waterproofing,
thickness and damages |
|
12 |
Aluminium |
Check for colour variation and
section sizes |
|
13 |
Paint |
Check for the coverage and
finishing |
|
14 |
Renovo |
Check for the colour variation and
coverage |
|
15 |
Electrical fitting |
Check for the Make, Colour &
Functioning |
As per the samples available |
16 |
Sanitary fitting |
Check for the make, colour &
damages |
|
17 |
C P Fitting |
Check for the Make |
As per the sample |
18 |
Hardware fittings |
Check for the Make and the Colour |
As per the sample |
19 |
Fabrication |
Check for the specifications |
As per the sample |
Sample Quality Audit (Download)
S.No |
Description |
Yes |
No |
NA |
Remarks |
1 |
Whether QA plan being
kept at site |
|
|
|
|
2 |
Whether Quality Check
list being Followed at Site |
|
|
|
|
3 |
Whether the NCR given
by PMC being closed within 48hrs |
|
|
|
|
4 |
Whether contractor has
appointed Qualified Quality Person |
|
|
|
|
5 |
Whether the Concrete
Pour card being signed by consultants, PMC & Project in charge |
|
|
|
|
6 |
Whether the Latest /
revised Drawings being used at site |
|
|
|
|
7 |
Is the old drawings
are superseded & properly Documented / Returned back to PMC |
|
|
|
|
8 |
Whether the Cement has
Stored Properly in Godown |
|
|
|
|
9 |
Whether Steel has
properly stacked in steel yard |
|
|
|
|
10 |
Whether Other A class
Materials are Properly Stored |
|
|
|
|
11 |
Whether the Material
are being tested before they use |
|
|
|
|
12 |
Whether the Material
Test reports being documented & certified by Project In charge/PMC In
charge |
|
|
|
|
13 |
Whether the Cubes are
casted, tested, audited & documented properly. |
|
|
|
|
14 |
Whether the Mix design
being approved by consultant |
|
|
|
|
15 |
Whether the sample
cubes being casted & tested as per approved mix design |
|
|
|
|
16 |
Whether the concrete
being poured in presence of PMC in charge |
|
|
|
|
17 |
Whether the contractor
has deployed Qualified safety officer |
|
|
|
|
18 |
Whether the contractor
has safety Manual, Is being implemented at site |
|
|
|
|
19 |
Whether Labors &
Staffs are Using the Safety Equipments |
|
|
|
|
20 |
Whether Hazardous area
being properly barricaded /Closed. |
|
|
|
|
21 |
Whether Safety Signage
Boards being displayed at site |
|
|
|
|
22 |
Whether Safety
Training to Staff & Labors being given. |
|
|
|
|
23 |
Whether Safety Nets
being used in slab. |
|
|
|
|
24 |
Whether the contractor
has maintained the work place & site of clean & neat |
|
|
|
|
25 |
Whether all the joints
being treated properly before continuation |
|
|
|
|
26 |
Whether all the
materials being used as per contract specification |
|
|
|
|
No comments:
Post a Comment