CALCULATION OF MATERIALS
FOR CONCRETE
For Concrete Mix 1:2: 4 (M15) -1 Cum
Add 50% for Wet Concrete, ie., 1.5 Cum (1.54 also can be taken)
Cement -1 part = 1.5/ (1+2+4) = 0.214 Cum
1 Cum of Cement = 30 Bags of Cement ( 1 Cum = 1440 Kg /50 = 30bags)
Cement required = 0.214 x 30 = 6.42 bags
Sand required = 0.214 x 2 = 0.428 Cum
Aggregate required = 0.214 x 4 = 0.856 Cum
FOR SOLID BLOCK MASONRY 8" tk. in CM 1:6 mix - 100 Sqm
Volume = 100 x 0.2 (Thickness of wall) Block size - 0.4 x 0.2 x 0.2
= 20 Cum
Approx. no. of blocks required = 20 / (0.4 x 0.2 x 0.2)
= 1250 Nos.
Volume of Mortar = 20-(0.39 x 0.19 x 0.19 x 1250) (Deduct 10mm for mortar thickness)
= 20 - 17.598
= 2.40 Cum
Blocks = 17.598 / (0.4 x 0.2 x 0.2)
= 1100 Nos.
Add 2% wastage = 22
Total Blocks required = 1122 Nos.
FOR WALL PLASTERING CM 1:4, 12 mm tk. - 100 Sqm
Volume = 100 x (12/1000) = 1.20 Cum
Add 30 - 35% as bulking of Sand = 0.36 Cum
Add 20% wastage of Sand = 0.312 Cum
Total = 1.872 Cum
For 1: 4 mix, 1 part = 1.872 / (1+4) = 0.374 Cum
Cement required = 0.374 x 30 = 10.77 bags
Sand required = 0.374 x 4 = 1.496 Cum
Mortar - increase 25% for dry mortar = 2.4 + 0.6 = 3.0 Cum (Upto 33% can be increased)
For 1: 6 mix = 3 / (1+6)
= 0.429 Cum
Cement Required = 0.429 x 30 = 12.50 bags
Sand = 0.429 x 6 = 2.57 Cum
FOR RED CLAY BRICK MASONRY 9" tk. in CM 1:6 mix - 100 Sqm
Size of Bricks (Traditional in India) - 225 x 112.5 x 75 incl. 10mm mortar joint.
Volume = 100 x 0.225 (Thickness of wall)
= 22.5 Cum
Approx. no. of bricks required = 22.5 / (0.225 x 0.1125 x 0.075)
= 11852 Nos.
Volume of Mortar = 22.5-(0.215 x 0.1025 x 0.065 x 11852) (Deduct 10mm for mortar thickness)
= 22.5 - 16.98
= 5.52 Cum
Bricks = 16.98 / (0.225 x 0.1125 x 0.075)
= 8944 Nos.
Add 2% wastage = 179
Total Bricks required = 9123 Nos. For 100 Sqm 9" tk. wall
CONVENTIONAL METHOD OF CALCULATION OF BRICKS
Size of Brick - 9" x 4.5" x 3" (0.75 x 0.375 x 0.25 ft)
Volume of Brick = 0.75 x 0.375 x 0.25 = 0.07 Cft.
No. of Bricks in 1Cft. = 1 / 0.07 =14.285 Bricks
Quantity of Bricks without mortar = 14.285 - 1.4285 (Deduct 10% for mortar coverage)
= 12.856 Bricks
Adding 5% wastage of Bricks = 0.6428
Total no of bricks = 13.49 for 1 Cft of Brick work
For 100 Cft Brick work = 1349 Bricks
CALCULATION OF AGGREGATES
For 1:1.5:3 mix
Quantity of Aggregate = Aggregate / (Cement+ Sand + Aggregate ) x 1.57
= 3/ (1+1.5+3) x 1.57 = 0.85 Cum
! Cum of Aggregate = 1500 to 1800 Kg
Let us assume 1650 Kg, Then 0.85 Cum Aggregate = 1650 x 0.85 = 1402.5 Kg.