IS 1200 – Methods of Measurement - Overview

IS 1200 – Methods of Measurement - Overview

Indian Standard for Measurement

What is IS 1200?

Full Title: IS 1200 - Methods of Measurement of Building and Civil Engineering Works

Published By: Bureau of Indian Standards (BIS)

Purpose: Standardize measurement methods for construction work to ensure uniformity and avoid disputes.

Structure: 28 Parts covering different work categories

Legal Status:

  • Referenced in government contracts (mandatory)
  • Reference standard in private contracts (best practice)
  • Basis for arbitration/disputes on quantities

IS 1200 - 28 Parts:


Part 1 (1992): Earthwork

Part 2 (1974): Piling

Part 3 (1965): Cement Concrete Work (Superseded by Part 5)

Part 4 (1967): Structural Steel Work

Part 5 (1982): Concrete Work (RCC, Plain Concrete)

Part 6 (1972): Masonry (Brickwork, Stonework, Blockwork)

Part 7 (1972): Roofing and Sheeting (Tiles, Metal sheets)

Part 8 (1981): Doors, Windows and Ventilators

Part 9 (1992): Plastering, Pointing and Finishing

Part 10 (1992): Water Proofing and Damp Proofing

Part 11 (1993): Drainage Work

Part 12 (1982): Road Work

Part 13 (1983): Railway Track Work

Part 14 (1967): Underground Sewer and Water Supply

Part 15 (1968): Canal Work

Part 16 (1974): Electrical Work

Part 17 (1977): Glazing Work

Part 18 (1995): White Washing, Colour Washing, Distempering

Part 19 (1981): Reinforcement for RCC Work

Part 20 (1982): Finishing of Floors and Other Surfaces

Part 21 (1995): Dam, Aqueduct and Reservoir

Part 22 (1982): Wood Work (Carpentry and Joinery)

Part 23 (1974): Painting

Part 24 (1981): Timber Treatment

Part 25 (1982): Plumbing and Sanitary Installations

Part 26 (1983): Bridge Work

Part 27 (1987): Insulation Work (Thermal, Acoustic)

Part 28 (1981): Asbestos Cement Works


Key Parts for Building Construction:

Most Used (90% of building work):

  • Part 1: Earthwork (excavation, filling, grading)
  • Part 5: Concrete work (RCC, PCC)
  • Part 6: Masonry (brickwork, blockwork)
  • Part 9: Plastering and pointing
  • Part 10: Waterproofing
  • Part 19: Reinforcement (steel bars)
  • Part 20: Flooring
  • Part 23: Painting

Specialized (as needed):

  • Part 2: Piling (if foundation has piles)
  • Part 8: Doors and windows (if measured separately)
  • Part 22: Woodwork (if significant carpentry)
  • Part 25: Plumbing (sanitary, water supply)

How IS 1200 Works:

Each Part Contains:

  1. Scope: What work is covered
  2. Units of Measurement: m, m², m³, kg, nos, etc.
  3. General Rules: What is included in measurement
  4. Specific Rules: Item-wise measurement methods
  5. Deductions: What openings/items to deduct
  6. Exclusions: What is NOT measured
  7. Examples: Illustrative calculations

Example - IS 1200 Part 6 (Brickwork):

Scope: Measurement of brick masonry in walls, columns, arches, etc.

Unit: Cubic meter (m³) for rate contracts Square meter (m²) for item rate contracts (9" wall, 4.5" wall separately)

General Rules:

1. Measured in cubic meters (length × height × thickness)

2. No deduction for:

   - Openings up to 0.1 m² each

   - Wooden or steel members up to 0.05 m² cross-section

3. Deduct in full:

   - Openings exceeding 0.1 m² each

   - Bearings of beams, lintels

4. Add separately:

   - Raking, corbelling, curved work (if >5% extra)

5. Mortar is included (not measured separately)

6. Scaffolding is included (not measured separately)

What This Means:

Example: Wall 5m long × 3m high × 0.23m (9") thick with 1 door opening 1m × 2m

 

Gross volume: 5 × 3 × 0.23 = 3.45 m³

Door opening: 1 × 2 × 0.23 = 0.46 m² (exceeds 0.1 m², so deduct)

Net brickwork: 3.45 - 0.46 = 2.99 m³

 

Payment: 2.99 m³ @ rate per cum


Importance of Following IS 1200:

Legal:

  • Contract clause: "Measurement as per IS 1200"
  • Disputes resolved based on IS 1200 interpretation
  • Arbitrator's decision references IS 1200

Practical:

  • Uniform understanding (contractor, engineer, client)
  • No ambiguity in what's included/excluded
  • Fair payment (standardized method)

Financial:

  • Incorrect measurement = Incorrect payment
  • Knowing IS 1200 = Claiming what's rightfully yours
  • Example: Forgetting to claim raking in brickwork = 5-8% loss

IS 1200 PART 1 - EARTHWORK

Title: Measurement of Excavation and Filling

Scope: All earthwork including excavation, filling, grading, leveling, ramming.

Unit of Measurement: Cubic meter (m³)


Critical Rule 1: In-Situ Measurement

Earthwork is ALWAYS measured in the INITIAL STATE (before excavation)

 

Example:

  Excavation required: 1,000 m³ (in-situ, before digging)

  After excavation, soil swells to: 1,300 m³ (loose state, 30% swell)

 

  Payment: For 1,000 m³ ONLY

 

  You do NOT get paid for swell volume!

Rationale: Payment for actual work, not bulking due to loosening.


Critical Rule 2: Classification of Soil

IS 1200 Part 1 recognizes different soil types:

1. Ordinary Soil (Earth)

   - Easy to dig with pick and shovel

   - Example: Clay, loamy soil, sand

 

2. Hard Soil

   - Requires pick, crowbar, mechanical equipment

   - Example: Gravel, dense clay, soft murrum

 

3. Soft Rock (Disintegrated)

   - Requires mechanical equipment, some blasting

   - Example: Weathered rock, laterite

 

4. Hard Rock

   - Requires blasting

   - Example: Granite, basalt, hard sedimentary rock

Why It Matters: Different rates for different soil types (rock excavation costs 3-5× ordinary soil)

Payment:

If BOQ says: "Excavation in ordinary soil" but you encounter rock

→ Rate revision claim (extra item rate for rock)

→ Dispute avoided if soil properly classified upfront


Measurement Rules - Excavation:

1. Foundation Excavation:

Measured: Length × Width × Depth (all in meters)

 

Width measured: Trench width (foundation + working space)

  Foundation width: As per drawing

  Working space: 500mm each side (typical)

  Total width = Foundation width + 1000mm

 

Depth measured:

  From NGL (Natural Ground Level) to formation level

  OR as specified in drawings

 

Example:

  Foundation: 10m long × 1m wide × 2m deep (from NGL)

  Working space: 0.5m each side

  Measured width: 1 + 0.5 + 0.5 = 2m

 

  Excavation quantity: 10 × 2 × 2 = 40 m³

2. Basement Excavation:

Measured: Gross area × depth

 

Deductions:

  - Existing structures to remain (if any)

  - Trees beyond 0.3m girth (measured separately)

 

No deduction for:

  - Internal walls (excavate full basement, then build walls)

  - Columns, pillar bases

 

Example:

  Basement: 20m × 15m × 3m deep

  Quantity: 20 × 15 × 3 = 900 m³

3. Removal of Excavated Material:

Measured separately if distance > 50m

 

Item description specifies:

  - "Excavation and disposal within 50m"

  - "Removal beyond 50m for every additional 50m or part thereof"

 

Lead distance: Horizontal distance from excavation to disposal point

 

Example:

  Excavation: 1,000 m³

  Disposal point: 180m away

 

  Items to measure:

    1. Excavation: 1,000 m³ (up to 50m included)

    2. Extra lead (50-100m): 1,000 m³

    3. Extra lead (100-150m): 1,000 m³

    4. Extra lead (150-200m): 1,000 m³


Measurement Rules - Filling:

1. Filling Under Floors:

Measured: Area × Average thickness

 

Include:

  - Compaction (in measurement description, e.g., "in layers of 200mm")

  - Watering and ramming

 

Exclude:

  - Earth removed and re-used (filling with excavated earth)

  - Measure only EXTRA earth brought from outside

 

Example:

  Floor area: 100 m² × 0.6m thick filling

  Excavated available: 50 m³

  Required: 100 × 0.6 = 60 m³

 

  Measure filling with excavated earth: 50 m³ (free, just spreading cost)

  Measure filling with brought earth: 10 m³ (material + transport cost)

2. Backfilling Trenches:

Measured: Trench volume - Foundation volume

 

Example:

  Trench excavation: 40 m³ (from earlier example)

  Foundation (masonry/concrete): 10m × 1m × 0.5m = 5 m³

 

  Backfilling required: 40 - 5 = 35 m³

 

  If excavated soil re-used: 35 m³ backfill with excavated earth

  If not suitable: 35 m³ backfill with selected soil (brought from outside)


Common Mistakes - Earthwork:

Mistake 1: Paying for Swell

Wrong: Measure after excavation (1,300 m³ loose)

Right: Measure in-situ before excavation (1,000 m³)

Loss if wrong: 30% overpayment

Mistake 2: Not Classifying Soil

Wrong: All excavation in "ordinary soil" (but 30% is rock)

Right: Separate measurement - 700 m³ ordinary, 300 m³ rock

Impact: Rock costs 3× more, ₹(300 × ₹800) = ₹2.4 lakhs extra deserved

Mistake 3: Deducting Small Openings

Wrong: Deduct column pits from basement excavation

Right: No deduction (excavate full basement)

Loss if wrong: Under-measurement, lower payment

Mistake 4: Ignoring Working Space

Wrong: Foundation trench = foundation width only (1m)

Right: Foundation + working space (2m)

Loss if wrong: 50% under-measurement!


IS 1200 PART 5 - CONCRETE WORK

Title: Measurement of RCC and Plain Concrete

Scope: All concrete work - plain cement concrete (PCC), reinforced cement concrete (RCC), pre-stressed concrete.

Unit of Measurement: Cubic meter (m³)


Critical Rule 1: Gross Volume

Concrete is measured GROSS (including embedded items)

 

Include in concrete volume:

  - Reinforcement steel (bars, mesh)

  - Embedded pipes, conduits

  - Embedded anchor bolts, inserts

  - Formwork (shuttering) is not deducted

 

Do NOT deduct:

  - Reinforcement (even though it occupies space)

  - Small embedments

 

Example:

  RCC Column: 0.3m × 0.4m × 3.5m

  Steel inside: 8 nos 20mm dia bars + stirrups (~ 0.01 m³)

 

  Measured concrete: 0.3 × 0.4 × 3.5 = 0.42 m³ (gross, no deduction for steel)

 

  Reinforcement measured separately as per Part 19 (in kg)

Rationale: Simplicity - deducting small volumes creates complexity without significant accuracy gain.


 

Critical Rule 2: Formwork Included

Unless specified otherwise, formwork is INCLUDED in concrete rate

 

Measurement description specifies:

  - "Including cost of formwork and its removal"

  - OR separate item: "Providing and removing formwork to ___"

 

For rate analysis:

  If formwork NOT separate, include ₹450-800/m³ in concrete rate

  If formwork separate, exclude from concrete rate


Measurement Rules - Foundations:

1. Plain Cement Concrete (PCC) in Foundation:

Measured: Length × Width × Thickness

 

Example:

  Foundation: 10m long × 2m wide × 0.15m thick (PCC bed)

 

  Quantity: 10 × 2 × 0.15 = 3.0 m³

 

  Item description: "Plain cement concrete M15 grade in foundation

  including formwork, compaction, curing as per IS 456"

2. RCC Footings:

Measured: As per individual footing dimensions

 

For isolated footings:

  Each footing: Length × Width × Depth

  Total: Sum of all footings

 

Example:

  10 footings, each 2m × 2m × 0.5m

  Per footing: 2 × 2 × 0.5 = 2.0 m³

  Total: 10 × 2.0 = 20 m³


Measurement Rules - Columns:

Measured: Cross-section × Height

Height measured:

  From: Top of footing/plinth

  To: Soffit of beam above (underside of beam)

 

  NOT to top of beam (that's part of beam)

 

Example:

  Column: 0.3m × 0.4m cross-section

  Number of columns: 20

  Floor height: 3.5m (floor to soffit of beam)

 

  Per column: 0.3 × 0.4 × 3.5 = 0.42 m³

  Total G.F. columns: 20 × 0.42 = 8.4 m³

 

  Item: "RCC M30 in columns including formwork" = 8.4 m³

Deductions:

No deduction for:

  - Reinforcement steel

  - Openings/recesses < 0.1 m² cross-section

 

Deduct:

  - Large recesses/openings > 0.1 m² (rare in columns)


Measurement Rules - Beams:

Measured: Cross-section × Length

Length measured:

  For independent beams: Center to center of supports

  For continuous beams: Full length (don't deduct column widths)

 

Height measured:

  From: Top of slab (if monolithic)

  To: Soffit of beam

 

  If beam is independent: Full depth

 

Example:

  Beam: 0.3m wide × 0.5m deep (below slab)

  Length: 5m (between column centers)

  Number: 10 beams

 

  Per beam: 0.3 × 0.5 × 5 = 0.75 m³

  Total: 10 × 0.75 = 7.5 m³

Monolithic Beam-Slab:

Beam and slab cast together (most modern construction)

 

Measure beam:

  Width × Depth (excluding slab thickness) × Length

 

Measure slab:

  Area × Thickness (full area, no deduction for beam width)

 

Example:

  Room: 5m × 4m

  Slab: 0.15m thick

  Beam (on all 4 sides): 0.3m wide × 0.5m deep

 

  Slab: 5 × 4 × 0.15 = 3.0 m³

  Beams:

    2 beams (5m long): 2 × (0.3 × 0.5 × 5) = 1.5 m³

    2 beams (4m long): 2 × (0.3 × 0.5 × 4) = 1.2 m³

    Total beams: 2.7 m³

 

  Total concrete: 3.0 + 2.7 = 5.7 m³


Measurement Rules - Slabs:

Measured: Area × Thickness

Area: Gross area (no deduction for beams if monolithic)

 

Deductions:

  - Openings > 0.5 m² (e.g., staircase opening, lift well)

  - Skylights, large vents

 

No deduction for:

  - Openings < 0.5 m² (small vents, pipes)

  - Beams (if monolithic)

  - Columns passing through

 

Example:

  Slab: 10m × 8m × 0.15m thick

  Opening (staircase): 2m × 1.5m = 3 m² (deduct)

  Small vent: 0.4m × 0.4m = 0.16 m² (don't deduct)

 

  Gross: 10 × 8 = 80 m²

  Less opening: 3 m²

  Net area: 77 m²

 

  Quantity: 77 × 0.15 = 11.55 m³


Measurement Rules - Special Items:

1. Sunken Slabs:

Measured separately (different level)

 

Example:

  Bathroom slab sunken by 300mm for waterproofing

  Area: 2m × 1.5m

  Thickness: 0.15m

  Sunk depth: 0.3m

 

  Regular slab: 2 × 1.5 × 0.15 = 0.45 m³

  Plus sides: 2(2 + 1.5) × 0.3 × 0.15 = 0.315 m³

 

  OR measure as separate item: "RCC in sunken slab" = 0.77 m³

2. Staircases:

Measured: Developed area (following slope) × Average thickness

 

OR: Volume calculation (waist slab + treads)

 

Example:

  Flight: 10 treads, 0.25m tread, 0.15m rise

  Width: 1.2m

  Waist slab thickness: 0.15m

 

  Slope length: √(10×0.25)² + (10×0.15)² = 2.92m

  Area: 2.92 × 1.2 = 3.5 m²

  Concrete: 3.5 × 0.15 = 0.525 m³

 

  Plus treads volume if separate

3. Chajjas, Sunshades:

Measured: Area × Thickness

 

Include projection in area

 

Example:

  Chajja: 5m long × 0.6m projection × 0.1m thick

  Quantity: 5 × 0.6 × 0.1 = 0.3 m³


IS 1200 PART 6 - MASONRY WORK

Title: Measurement of Brickwork and Blockwork

Scope: Brick masonry, stone masonry, cement block masonry in walls, columns, arches.

Unit of Measurement: Cubic meter (m³) for rate contracts
OR Square meter (m²) for item rate contracts specifying wall thickness


Critical Rule 1: Openings Deduction

Deduct openings ONLY if each exceeds 0.1 m²

 

Examples:

 

Door opening: 1m × 2m = 2 m² → DEDUCT (>0.1 m²)

Window opening: 1.2m × 1.5m = 1.8 m² → DEDUCT (>0.1 m²)

Small vent: 0.3m × 0.3m = 0.09 m² → DON'T DEDUCT (<0.1 m²)

Pipe hole: 0.15m × 0.2m = 0.03 m² → DON'T DEDUCT (<0.1 m²)

 

Rationale:

  Small openings require cutting, wastage → labor compensates for material saved


Critical Rule 2: Mortar Included

Brickwork measurement includes mortar

 

Item description: "Brickwork in CM 1:6" means:

  - Bricks

  - Cement mortar 1:6

  - Laying, jointing

  - Scaffolding

  - Curing

 

Do NOT measure cement and sand separately for mortar

(Already included in brickwork rate)


Measurement Rules - Walls:

1. External Walls:

Measured: Length × Height × Thickness

 

Length:

  Outside to outside (for external walls)

  OR centerline method (explained later)

 

Height:

  From: Top of plinth/floor

  To: Bottom of roof slab/ceiling

 

Thickness:

  As per specification (9", 4.5", 13.5")

  In meters: 9" = 0.23m, 4.5" = 0.115m, 13.5" = 0.345m

 

Example:

  External wall: 15m long × 3m high × 0.23m (9") thick

  2 windows: Each 1.2m × 1.5m = 1.8 m² (DEDUCT)

  1 door: 1m × 2m = 2 m² (DEDUCT)

 

  Gross: 15 × 3 × 0.23 = 10.35 m³

  Less windows: 2 × (1.2 × 1.5 × 0.23) = 0.828 m³

Less door: 1 × 2 × 0.23 = 0.46 m³ Net brickwork: 10.35 - 0.828 - 0.46 = 9.062 m³

 

2. Internal Walls:

Measured: Length × Height × Thickness

Length: Wall to wall (for partition walls) OR centerline of walls

Deductions:

  • Door openings (internal doors typically 0.9m × 2m = 1.8 m² → DEDUCT)

Example: Internal wall: 4m long × 3m high × 0.115m (4.5") thick 1 door: 0.9m × 2m = 1.8 m²

Gross: 4 × 3 × 0.115 = 1.38 m³ Less door: 0.9 × 2 × 0.115 = 0.207 m³ Net: 1.17 m³

 

Centerline Method (Shortcut for Complex Plans):

Concept:

Instead of calculating each wall separately with junctions, use total centerline length.

 

Formula:

Brickwork = Centerline length × Height × Thickness

 

Example:

Room: 5m × 4m (external dimensions) Wall thickness: 0.23m (9") Height: 3m No openings

Method 1 - Individual walls: 2 walls (5m long): 2 × 5 × 3 × 0.23 = 6.9 m³ 2 walls (4m long): 2 × 4 × 3 × 0.23 = 5.52 m³ BUT: Overlap at corners (counted twice) Correction needed: Complex

Method 2 - Centerline: External perimeter: 2(5 + 4) = 18m Centerline: 18m (measured at center of wall)

Brickwork: 18 × 3 × 0.23 = 12.42 m³ ✓ Accurate

 

When to Use:

- Complex plans with many walls

- Multiple rooms with junctions

- Saves time, reduces errors

 

When NOT to Use:

- Walls of different thickness (need separate calculation)

- Many openings (deduct individually anyway)

 

Measurement Rules - Special Items:

 

1. Raking/Corbelling:

Measured separately if significant (>5% extra)

Raking: Sloped brickwork (gables, ramps) Corbelling: Projecting courses

Example: Gable end: Triangular brickwork Base: 5m, Height: 2m, Thickness: 0.23m Area: 0.5 × 5 × 2 = 5 m² Volume: 5 × 0.23 = 1.15 m³

Item: "Raking in brickwork" = 1.15 m³ @ higher rate (+15-20%)

 

2. Arches:

Measured: Developed length × Width × Thickness

Developed length: Following curve

Example: Semi-circular arch over door Span: 1m, Width (wall thickness): 0.23m Thickness of arch: 0.23m

Developed length: π × 1 ÷ 2 = 1.57m Volume: 1.57 × 0.23 × 0.23 = 0.083 m³

 

3. Curved Walls:

Measured: Curved length × Height × Thickness

Use flexible tape to measure curve OR calculate from radius

Extra rate for curvature (more labor, wastage)

 

Common Mistakes - Masonry:

 

Mistake 1: Deducting Small Openings

Wrong: Deduct every vent, pipe hole Right: Deduct only openings >0.1 m² Impact: Under-measurement by 2-5%

 

Mistake 2: Measuring Mortar Separately

Wrong: Measure bricks, then cement, then sand for mortar Right: Brickwork includes everything (just measure brickwork) Impact: Confusion, potential double-counting

 

Mistake 3: Forgetting Corner Overlaps

Wrong: Measure all 4 walls full length → Corners counted twice Right: Use centerline method OR deduct overlap Impact: Over-measurement by 5-8%

 

Mistake 4: Wrong Thickness Conversion

Wrong: 9" wall = 0.25m (rough approximation) Right: 9" = 9 × 0.0254m = 0.2286m ≈ 0.23m (accurate) Impact: 8% error in thickness → 8% error in quantity

 

No comments:

IS 1200 – Methods of Measurement - Overview

IS 1200 – Methods of Measurement - Overview Indian Standard for Measurement What is IS 1200? Full Title: IS 1200 - Methods of Measure...