VACUUM DEWATERED FLOORING - METHODOLOGY & CHECKLIST

 VACUUM DEWATERED FLOORING (VDF)

A. PREPARATION OF SUB-GRADE 

Sub-grade should be laid according to specifications, levels as recommended by the consultant

Ensure that proper consolidation of the sub-grade has been achieved before proceeding for the PCC bed

Provide and lay PCC bed above the sub-grade as per thickness mentioned in the drawing

Provide a reinforcement mesh as per specification and the drawings

Clean the entire PCC bed with water before concreting 

B. DEWATERING AND FINISHING

Concreting should be carried out with concrete of right grade and slump. (See: Concreting)

Concrete intermediate/ alternate panels shuttered by ISMC runners or continuous bull marks. 

Ensure proper expansion joints as per working drawings and protected


Dewatering mat to be used to remove excess water from the concrete surface to ensure concrete of the highest strength is achieved.

The dewatering mat should be properly laid to prevent air leakage. Care should be taken in ensuring that excess water does not enter the dewatered area.

After initial set of concrete (2-3 hours), the top surface of concrete is finished using a power trowel. Care should be taken that no impact load is transferred to the finished surface.

No load or stepping on concrete should be avoided, before initial set of finished concrete.

Heavy vibrations should be avoided in vicinity of the VDF area.

C. TESTING OF CONCRETE

SLUMP TEST

Conduct slump cone test, one during the start, one at midday and one towards the close of days work.

Any load under suspicion can be checked for slump on case-to-case basis.

CUBE TEST

The sample is made at point of discharge of mixture.

Take 3 samples after 7 days and 3 samples after 28 days strength.

Every 100 cum or 10 batches of concrete (whichever is smaller) should be represented by a sample of test cubes.

For concrete manufactured at site, there must be representative samples for the day’s work and for different elements like footing, slab, column and wall.

Test results should be discussed with the project in-charge even if the results are satisfactory

In case of cube failure, the element to be identified and non-destructive test to be conducted.


TOOLS TO BE USED BY TRADESMEN

Required tools must be available at site to ensure correct work. Basic tools of the concreting gang are:

1. Vacuum Dewatering machine

2. Power Trowels

3. Trowels

4. Gum boots

5. Dumpy levels

6. Spirit levels 1-3m

7. Measuring tape

8. Screed finishing darby

9. Steel trash tracks

10. Hammer

11. Leveling trowels

12. Wheelbarrow

13. Long handle Aluminium leveler with spirit level

14. Masons brushes and buckets

15. High pressure water cleaners 


 INSPECTION METHODOLOGY FOR QUALITY ASSURANCE

1. Personnel 

Ensure all personnel are wearing gumboots

2. Before Concreting

Ensure shuttering is sealed with sealing tape so as there is no leakage of slurry

All reinforcements are in place especially chairs

All cover blocks damaged during reinforcement layout are replaced

3. During Concreting

Ensure proper grade of concrete as recommended by the consultant is employed

Ensure proper expansion joints as per working drawings and protected 

Check the top surface of fresh concrete for eveness of top surface

     4. After Concreting

Top surface is checked for straightness using Aluminium straight edge or leveling thread as the case may be.

Curing carried as per guidelines 

Water level is maintained during ponding

Ensure the cube test results are available at the end of the term indicated

 TOOLS TO BE USED FOR QUALITY INSPECTION

1. Dumpy levels to check finished slab level

2. Aluminium straight edge 

3. Leveling thread

4. Spirit levels 1-3m

5. Measuring tape

6. All the relevant related drawings


No comments:

Challenges in Civil Engineering Projects

 Challenges in Civil Engineering Projects Civil engineering projects face a multitude of challenges that can impact their success. Here are ...